Scope:
High priority project to increase the square footage and provide new accommodation of services for the Veterans’ Resource Center (VRC)/Student Activities Center (SAC) Expansion.

Status:
Demolition of the site continues. Removal of the existing landscaping and planning for the relocation of site utilities are in progress. Discussions on ways to remediate Piazza water leaks affecting the SAC are ongoing. That portion of the project will not be funded by Measure J. The Campus Project Team and Construction Management Team are working together on noise mitigation measures during finals week and Graduation ceremonies for Spring 2019. In addition, the campus is developing a letter to send to the local residents about the project scope, benefits, schedule, and potential noise impacts.

Project Estimate:
$13,500,000

Campus Project Manager:
Ryan Lippmann

District Director, Facilities Planning & Construction:
Richard Williams

Program Management:
MAAS Companies


preview