Project Overview

The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.

 

Status: Close-Out

Project Costs: Measure J=$6,399,604; Local=$13,167,050

Architect of Record: Roesling Nakamura Terada Architects, Inc.

General Contractor: BN Builders, Inc.

Project Manager: John Erickson

Program Management: MAAS Companies

Construction Start: October 2023

Construction Completion: June 2025

New M&O Building - Project Site

__________________________________________________________________________

Construction Progress Pictures

Milestones

  • Financial Close-Out

Impacts and Closures

  • Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
  • Expect some noise during construction

Emergency Contact

  • Victor Vasquez (Lead Superintendent): (714) 732-4730
  • Rosendo Pantoja (Superintendent): (714) 352-1926

Q2 2026 Project Update

New Maintenance & Operations Building

June 

Design Builder, BN Builders, has addressed the remaining items required by the DSA Field Engineer, including the installation of an uninterruptible power supply to provide emergency power for the continued operation of the building’s automated doors in the event of an electrical outage.

The project was later reviewed by the Inspector of Record and signed off as the project met the requirements of completion. DSA certification is expected to be achieved in the coming days, marking its conclusion.