Project Overview
The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.
Status: Close-Out
Project Costs: Measure J=$6,399,604; Local=$13,167,050
Architect of Record: Roesling Nakamura Terada Architects, Inc.
General Contractor: BN Builders, Inc.
Project Manager: John Erickson
Program Management: MAAS Companies
Construction Start: October 2023
Construction Completion: June 2025
New M&O Building - Project Site
__________________________________________________________________________
Construction Progress Pictures
Milestones
- Financial Close-Out
Impacts and Closures
- Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
- Expect some noise during construction
Emergency Contact
- Victor Vasquez (Lead Superintendent): (714) 732-4730
- Rosendo Pantoja (Superintendent): (714) 352-1926
Q2 2026 Project Update
New Maintenance & Operations Building
June
Design Builder, BN Builders, has addressed the remaining items required by the DSA Field Engineer, including the installation of an uninterruptible power supply to provide emergency power for the continued operation of the building’s automated doors in the event of an electrical outage.
The project was later reviewed by the Inspector of Record and signed off as the project met the requirements of completion. DSA certification is expected to be achieved in the coming days, marking its conclusion.







