Project Overview
The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.
Status: Construction
Project Costs: Measure J=$6,399,604; Local=$11,121,135
Architect of Record: Roesling Nakamura Terada Architects, Inc.
General Contractor: BN Builder, Inc.
Project Manager: Oscar Saghieh
Program Management: MAAS Companies
New M&O Building - Project Site
__________________________________________________________________________
Construction Progress Pictures
Upcoming Milestones:
- Foundations to begin in early March 2024
- Column Footings & Grade Beams to begin in early March 2024
- Structure to begin in late March 2024
Impacts and Closure
- Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
- Expect some noise during construction
Emergency Contract:
- Robert Mendoza - Assistant Superintendent : 714-732-3824
Q1 2024 Project Update
New Maintenance & Operations Building
The New M&O Building project has experienced weather delays during the period of inclement weather in late January and February that resulted in soil saturated with rainwater. Measures were underway to pump water from the site and the excavated locations. Work is in progress to restore the excavation levels following the storms in early February. The Design-Build team is developing mitigation measures for impending storms to enable for a faster recovery as soil conditions allow machinery to operate.
The building pad certification is targeted for the end of February. Excavations for grade beams and column footings will be upcoming after the severe winter storms pass in February.
The Design-Builder held a pre-commissioning meeting with Commissioning Agent (CxA) Glumac in preparation for developing a commissioning plan for this project. A kick-off session for the commissioning meeting occurred in the first weeks of February. A preliminary commissioning plan is under development.