Project Overview
Prior to the start of the Anaheim Tower First Floor Life/Safety Renovation project, involving repairs due to water intrusion at the upper deck parking lot, most first-floor activities were relocated to temporary classrooms and facilities located at the East Parking Lot of the Anaheim-NOCE Campus. Approximately 14 new temporary modular buildings were procured for NOCE's ongoing instruction and administrative activities. Relocation activities will ensue from the Euclid Center, Building B, and Swin Space — Interim Housing in phases between May and August 2025.
Status: Close-Out
Project Estimate: Measure J=$1,650,000 ; RDA and Local=$1,913,335;
Architect of Record: SVA Architects, Inc.
General Contractor: RT Contractor Corp
Project Manager: Matt Pirayeh
Program Management: MAAS Companies
Swing Space / Interim Housing - Project Site
_____________________________________________________________________
Construction Progress Pictures
Impacts and Closure
- Work is scheduled Monday - Friday from 7:30 to 5:30 PM
- Expect some noise during the placement of the modular buildings
- Users of the East Parking Lot will be redirected to the main parking lot and west parking lot during construction.
- Access to shipping and receiving is unaffected.
Emergency Contact:
Matt Pirayeh: (310) 739-1198
Q1 2026 Project Update
Swing Space Projects / Interim Housing
January - February
The District negotiated final costs with Mobile Modular associated with addressing modifications to facilitate the modulars’ usability for the duration of educational and administrative activities for the duration of swing space activities. The purchase order was closed-out with savings returned to budget.
As part of final close-out, the remaining balances have been reallocated to support current and future projects. The project is now closed-out.