Project Overview

The Anaheim Tower First Floor Life/Safety Renovation project will include renovations to improve the building’s durability by mitigating water intrusion issues. Enhancements to the parking areas and to access surrounding the main tower are also planned including an improved path of travel for all users to more easily access the main entrance points to the tower.

 

Status: Bidding

Project Estimate: Measure J= $3,783,000; State= $10,330,000; RDA= $646,887

Architect of Record: SVA Architects, Inc.

General Contractor: PCL Construction

Project Manager: Matt Pirayeh

Program Management: MAAS Companies

Anaheim Tower First Floor Life/Safety Renovation - Project Site

__________________________________________________________________________

Current Deficiencies

Upcoming Milestones:

  • Mobilization late February 2024
  • Site Demolition to begin early March 2024

Impacts and Closure:

  • Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
  • Expect some noise, dust, and loss of use parking lot during construction

 

Emergency Contract:

  • Primary Contact: Matt Pirayeh - Project Manager 310-739-1198
  • Secondary Contact: Jon Kim - Project Engineer - 323-745-7285

Q1 2024 Project Update

Anaheim Campus Tower First Floor Life/Safety Renovation

In late February, PCL Construction initiated mobilization activities at the project site, starting with the perimeter fencing and windscreen placement. Trailers for the site team and Inspector of Record have been delivered and set in place on-site, and power and data connections are in progress.

Demolition and abatement work began on March 15, in accordance with State and Federal guidelines. Prior to its start, barricades were built in the interior hallways by the first week of March and crews installed protective materials around the kitchen equipment remaining in the Culinary Arts Department to avoid any damage from falling debris.

Work on the upper deck will occur in multiple phases in which the deck’s surface will be dismantled down to its structural components, where the existing expansion joints and water barriers will be replaced, and the parking surface will be rebuilt. The initial phase on the south side of the deck is anticipated to continue until June 2024 and occur alongside the current abatement work.