Project Overview
New signage will be installed on the building’s exterior to update the existing marquee signage located off Romneya Drive and the signage above the canopy at the Tower’s main entrance points. On the interior, directory and directional signage is planned to be updated next to elevators at each floor.
Status: Implementation
Project Estimate: Measure J=$1,337,431; Local=$59,000
Architect of Record: Westberg + White
Specialty Contractor: KYA Group, Inc.
Project Manager: Cora Baldovino
Program Management: MAAS Companies
Construction Start: November 2024
Construction Completion: Fall 2026
Upcoming Milestones
- Signage Fabrication
Develop Interior/Exterior Signage - Project Site
______________________________________________________________________
Implementation Pictures
Impacts and Closures
- Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
- Expect some noise, dust, and loss of use parking lot during construction
Emergency Contact:
- TBD
Q1 2026 Project Update
Develop Interior and Exterior Signage
January
In December, Architect of Record, PBK Architects, approved all signage drawings; the drawings were then sent for fabrication.
Meanwhile, crews from installer, KYA Group, began forming the concrete base that will hold each type of sign. The process began with wooden molds, reinforcement bar placement, followed by concrete pouring and curing. Once dry, the molds were removed and the bases are now ready for signage installation once they arrive on site. Signage installation is anticipated to take approximately two days.
The exterior signage scope of work is anticipated to conclude in early March 2026.
Work on the interior signage is anticipated to resume later this year.






