Project Overview

New signage will be installed on the building’s exterior to update the existing marquee signage located off Romneya Drive and the signage above the canopy at the Tower’s main entrance points. On the interior, directory and directional signage is planned to be updated next to elevators at each floor.

 

Status: Implementation

Project Estimate: Measure J=$1,337,431; Local=$59,000

Architect of Record: Westberg + White

Specialty Contractor: KYA Group, Inc.

Project Manager: Cora Baldovino

Program Management: MAAS Companies

Construction Start: November 2024

Construction Completion: Fall 2026

 

Upcoming Milestones

  • Signage Fabrication

Develop Interior/Exterior Signage - Project Site

______________________________________________________________________

Implementation Pictures

 

Impacts and Closures

  • Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
  • Expect some noise, dust, and loss of use parking lot during construction

Emergency Contact: 

  • TBD

Q1 2026 Project Update

Develop Interior and Exterior Signage

January

In December, Architect of Record, PBK Architects, approved all signage drawings; the drawings were then sent for fabrication.
Meanwhile, crews from installer, KYA Group, began forming the concrete base that will hold each type of sign. The process began with wooden molds, reinforcement bar placement, followed by concrete pouring and curing. Once dry, the molds were removed and the bases are now ready for signage installation once they arrive on site. Signage installation is anticipated to take approximately two days.
The exterior signage scope of work is anticipated to conclude in early March 2026.
Work on the interior signage is anticipated to resume later this year.