Project Overview
The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.
Status: Construction
Project Costs: Measure J=$6,399,604; Local=$11,121,135
Architect of Record: Roesling Nakamura Terada Architects, Inc.
General Contractor: BN Builder, Inc.
Project Manager: Oscar Saghieh
Program Management: MAAS Companies
New M&O Building - Project Site
__________________________________________________________________________
Construction Progress Pictures
Upcoming Milestones:
- Foundations for elevator pit
- Column footings and grade beams
- Structure to begin in early April 2024
Impacts and Closure
- Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
- Expect some noise during construction
Emergency Contract:
- Robert Mendoza - Assistant Superintendent : 714-732-3824
Q1 2024 Project Update
New Maintenance & Operations Building
The recent rains in the region have impacted work on the foundations for this building. Crews are working on dewatering the site to allow the soil to dry off before returning to construction activities. The Building Pad was certified, elevator casing was installed, and wood formwork for the concrete pours was set in place. Excavation for the foundation beams to support the building masonry walls was underway in late March and completed in April.
The reinforcement bar was delivered to the site in early April. Crews then addressed its placement for the foundation footings and grade beams. Concrete pours are anticipated to begin in mid to late April. Once the structural concrete cures, crews will assemble the walls using large hollow CMU bricks.