Project Overview

The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.

 

Status: Close-Out

Project Costs: Measure J=$6,399,604; Local=$13,167,050

Architect of Record: Roesling Nakamura Terada Architects, Inc.

General Contractor: BN Builders, Inc.

Project Manager: John Erickson

Program Management: MAAS Companies

Construction Start: October 2023

Construction Completion: June 2025

New M&O Building - Project Site

__________________________________________________________________________

Construction Progress Pictures

Milestones

  • Financial Close-Out

Impacts and Closures

  • Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
  • Expect some noise during construction

Emergency Contact

  • Victor Vasquez (Lead Superintendent): (714) 732-4730
  • Rosendo Pantoja (Superintendent): (714) 352-1926

Q2 2026 Project Update

New Maintenance & Operations Building

March - June 

Amendment No. 3 comprising of Change Order Nos. 2 and 3, was presented to the Board of Trustees along with a Notice of Completion in late March. The Design Builder, BN Builders, is addressing the remaining final items, including an uninterrupted power supply required by the DSA Field Engineer to enable emergency power for the continued use of the building’s automated doors during an electrical outage.
The items were ordered and installed in the last week of April. The projects will be reviewed by the Inspector of Record and signed off if the projects meet the requirements of completion. DSA certification is expected to be achieved upon the conclusion of Inspector of Record review, marking the conclusion of the projects.