Project Overview

Located at the intersections of Chapman Avenue and Newell Street, the Chapman/Newell Instructional Building will be home to an array of student services vital to their success including the Campus Veterans’ Resource Center, Student Wellness Center (both medical and behavioral health), the Campus Food Bank, Umoja Community Program, Extended Opportunity Programs and Services (EOPS), CalWORKS, Cooperative Agencies Resources for Education (CARE)/Foster Youth Success Initiative (FYSI), a Multi-Cultural Center, and 2 instructional classrooms. In addition, there will be support functions including shared community storage, a department-wide copy, and a breakroom as well as a lactation room for the benefit of all users.

 

Status: Construction

Project Costs: Measure J=$28,302,917 Local= $1,667,120

Architect of Record: Roesling Nakamura Terada Architecs, Inc.

General Contractor: BN Builders, Inc.

Project Manager: Oscar Saghieh

Program Management: MAAS Companies

Anticipated Completion: Winter 2025

Chapman/Newell Building - Project Site

Chapman.Newell Legend Nearmap

__________________________________________________________________________

Construction Progress Pictures

Upcoming Milestones:

  • Foundation for elevator pit
  • Column footings and grade beams
  • Interior column footings
  • Slab on grade
  • Structure to begin in mid-April 2024

 

Impacts and Closures

  • Work is scheduled Monday through Friday from 7:30am to 5:30pm.
  • Pedestrian and traffic diversions will occur during portions of construction. Please follow detour signs set up for alternate pathways.
  • There will be some noise affecting the public for the duration of construction.

Emergency Contact:

  • Robert Mendoza - Assistant Superintendent - 714-732-3824

Q1 2024 Project Update

Chapman / Newell Instructional Building

Rain delays have significantly impacted the project, which has resulted in approximately 29 weather days; this amount exceeds the total number of weather-related delays factored into the baseline schedule. The Design-Builder assessed solutions to address the potential delays posed to the project schedule as it is on the critical path.

Concrete pours were completed for the remaining grade beams and elevator pit at the project site ahead of the storm's impact in the last weekend of March. Wood formwork was placed before the concrete pour for the slab-on-grade. Excavation activities were underway in the second week of April for plumbing and electrical conduits below the structure. By mid-April, underground utilities placement below the slab-on-grade neared completion. Testing has been conducted to ensure connections are compliant with code requirements. Back-fill activities will ensue upon completion followed by concrete pours in the last week of April.