Project Overview
Considered the first phase of the New Performing Arts Complex project, the Wilshire Chiller Plant will be relocated adjacent to its original location to accommodate the future construction of the New Performing Arts Complex in its original building footprint. The facilities deliver temperature control to the buildings in its vicinity, including the Wilshire Center. The new facility will provide the same service to the current buildings in addition to the new Performing Arts Complex. The relocation of the infrastructure will be carried in coordination with the local utility, Southern California Edison (SCE).
Status: Close-Out
Project Costs: Measure J=$16,487,409
Architect of Record: Pfeiffer Partners Architects, Inc.
General Contractor: Plumbing, Piping, Construction, Inc.
Project Manager: Aaron Choi
Program Management: MAAS Companies
Construction Start: May 2024
Completion: March 2026
Wilshire Chiller Plant - Project Site
Construction Progress Pictures
Upcoming Milestones
- Retention Release
Impacts and Closures
- Working is scheduled Monday - Friday From 7:00 AM to 4:30 PM
- Expect some noise during construction
Emergency Contact
- Nick Lopez: (714) 209-2386
Q3 2026 Project Update
Wilshire Chiller Plant Relocation
July
The project is undergoing the final stages of close-out. Close-out documents have been collected and archived. On June 23 the Board of Trustees approved the final deductive change order and Notice of Completion. The Notice of Completion was then filed with the Clerk-County Recorder on July 15. The Financial Team is working on finalizing the contract cost ahead of releasing retention to general contractor, PPC.




