Project Overview

Considered the first phase of the New Performing Arts Complex project, the Wilshire Chiller Plant will be relocated adjacent to its original location to accommodate the future construction of the New Performing Arts Complex in its original building footprint. The facilities deliver temperature control to the buildings in its vicinity, including the Wilshire Center. The new facility will provide the same service to the current buildings in addition to the new Performing Arts Complex. The relocation of the infrastructure will be carried in coordination with the local utility, Southern California Edison (SCE).

 

Status: Close-Out

Project Costs: Measure J=$16,487,409

Architect of Record: Pfeiffer Partners Architects, Inc.

General Contractor: Plumbing, Piping, Construction, Inc.

Project Manager: Aaron Choi

Program Management: MAAS Companies

Construction Start: May 2024

Completion: March 2026

 

Wilshire Chiller Plant - Project Site

wilshire site

Construction Progress Pictures

Upcoming Milestones

  • Retention Release

Impacts and Closures

  • Working is scheduled Monday - Friday From 7:00 AM to 4:30 PM
  • Expect some noise during construction

Emergency Contact

  • Nick Lopez: (714) 209-2386

 Q3 2026 Project Update

Wilshire Chiller Plant Relocation

July

The project is undergoing the final stages of close-out. Close-out documents have been collected and archived. On June 23 the Board of Trustees approved the final deductive change order and Notice of Completion. The Notice of Completion was then filed with the Clerk-County Recorder on July 15. The Financial Team is working on finalizing the contract cost ahead of releasing retention to general contractor, PPC.