Project Overview
Considered the first phase of the New Performing Arts Complex project, the Wilshire Chiller Plant will be relocated adjacent to its original location to accommodate the future construction of the New Performing Arts Complex in its original building footprint. The facilities deliver temperature control to the buildings in its vicinity, including the Wilshire Center. The new facility will provide the same service to the current buildings in addition to the new Performing Arts Complex. The relocation of the infrastructure will be carried in coordination with the local utility, Southern California Edison (SCE).
Status: Close-Out
Project Costs: Measure J=$16,487,409
Architect of Record: Pfeiffer Partners Architects, Inc.
General Contractor: Plumbing, Piping, Construction, Inc.
Project Manager: Aaron Choi
Program Management: MAAS Companies
Construction Start: May 2024
Completion: March 2026
Wilshire Chiller Plant - Project Site
Construction Progress Pictures
Q3 2026 Project Update
Wilshire Chiller Plant Relocation
September
The project is in the final stages of closeout, as the Notice of Completion was filed with the County Clerk-Recorder on July 15. The Financial Team finalized contract costs before releasing retention to the general contractor, PPC, in mid-August. The project achieved DSA certification on September 22. Final calibrations are taking place to ensure the chiller continues smooth operations at current temperatures.




