Project Overview

This project will restore the East Parking Lot to its original use after dismantling the temporary classrooms that were in operation for the duration of the Anaheim Tower First Floor/Life Safety Renovation project. 

Status: Construction

Project Costs: Measure J=$2,521,574

Architect of Record: PBK Architects 

Project Manager: Cora Baldovino

General Contractor: PaveWest

Construction Manager: TBD

Program Management: MAAS Companies

Construction Start: January 2026

Construction Completion: April 2026

Restore East Parking Lot - Project Site

Q2 2026 Project Update

March - June 

Crews have laid curbs to form the future parking stalls. Conduit installation was completed along with formwork to form the bases of the future lights in the parking lot. Asphalt paving took place in the final week of March, followed by a short curing period. Construction Field Instructions have been issued to facilitate the addition of light poles and electrical repairs for improved safety in the area. Long lead items non-critical to the completion of the project are being tracked by the Campus Project Team and general contractor.