Project Overview
The Anaheim Tower First Floor Life/Safety Renovation project will include renovations to improve the building’s durability by mitigating water intrusion issues. Enhancements to the parking areas and to access surrounding the main tower are also planned including an improved path of travel for all users to more easily access the main entrance points to the tower.
Status: Close-Out
Project Estimate: Measure J= $2,560,440; State= $7,059,000; RDA= $647,189
Architect of Record: SVA Architects, Inc.
General Contractor: PCL Construction
Project Manager: Matt Pirayeh
Program Management: MAAS Companies
Construction Start: February 2024
Anticipated Completion: December 2024
Anaheim Tower First Floor Life/Safety Renovation - Project Site
__________________________________________________________________________
Current Deficiencies
Upcoming Milestones
- Punch-list Activities
- Project Close-out
Impacts and Closures
- Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
- Expect some noise, dust, and loss of use parking lot during construction
Emergency Contact:
- Matt Pirayeh: (310) 739-1198
Q4 2024 Project Update
Anaheim Tower First Floor Life/Safety Renovation
The project is progressing into the final months, and several key tasks are nearing completion. The storm drain placement and electrical work related to the new drainage pump on the west side retaining wall excavation were completed in October. Once the area is backfilled, landscape irrigation work will be completed in early November. Expansion joints and truncated domes were installed in the first week of the month. Seal coating and striping were addressed over the second weekend in November, after the expected wet weekend at the start of the month. Roofing work on the perimeter planters continued into the second week of the month. Guardrail installation around the perimeter of the parking deck has been completed.
The modular buildings for the general contractor and inspector of record have been removed from the project site. Drywall patching is being done inside the building due to the replacement of water drinking fountains. Bathroom accessories were installed in early November, and tile installation is expected to be delivered in late November for placement. Punch-list walks for exterior spaces and bathrooms took place on November 14. Repairs related to the first interior punch-list walk in early October were addressed and are ready for a second visit to confirm completion. The close-out submittal process for manuals, warranties, and as-built drawings is underway.