Project Overview

The Anaheim Tower First Floor Life/Safety Renovation project will include renovations to improve the building’s durability by mitigating water intrusion issues. Enhancements to the parking areas and to access surrounding the main tower are also planned including an improved path of travel for all users to more easily access the main entrance points to the tower.

 

Status: Close-Out

Project Estimate: Measure J= $2,560,440; State= $7,059,000; RDA= $647,189

Architect of Record: SVA Architects, Inc.

General Contractor: PCL Construction

Project Manager: Matt Pirayeh

Program Management: MAAS Companies

Construction Start: February 2024

Anticipated Completion: March 2025

Anaheim Tower First Floor Life/Safety Renovation - Project Site

__________________________________________________________________________

Current Deficiencies

Upcoming Milestones

  • Project Close-out

Impacts and Closures

  • Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
  • Expect some noise, dust, and loss of use parking lot during construction

 

Emergency Contact:

  • Matt Pirayeh: (310) 739-1198

Q1 2025 Project Update

Anaheim Tower First Floor Life/Safety Renovation

PCL Construction completed activities from the Architect of Record’s final list of items. The DSA Field Engineer and Americans with Disabilities Act consultant, Marx Okubo recommended the addition of a mat at the second-floor entrance. The DSA Field Engineer also determined that additional truncated domes were required along the right edge of the driving ramp. Both items were completed in the third week of February. Upon completion of these activities, the project will finalize close-out in March.