Project Overview
The Anaheim Tower First Floor Life/Safety Renovation project will include renovations to improve the building’s durability by mitigating water intrusion issues. Enhancements to the parking areas and to access surrounding the main tower are also planned including an improved path of travel for all users to more easily access the main entrance points to the tower.
Status: Close-Out
Project Estimate: Measure J= $2,560,440; State= $7,059,000; RDA= $647,189
Architect of Record: SVA Architects, Inc.
General Contractor: PCL Construction
Project Manager: Matt Pirayeh
Program Management: MAAS Companies
Construction Start: February 2024
Anticipated Completion: February 2025
Anaheim Tower First Floor Life/Safety Renovation - Project Site
__________________________________________________________________________
Current Deficiencies
Upcoming Milestones
- Punch-list Activities
- Project Close-out
Impacts and Closures
- Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
- Expect some noise, dust, and loss of use parking lot during construction
Emergency Contact:
- Matt Pirayeh: (310) 739-1198
Q1 2025 Project Update
Anaheim Tower First Floor Life/Safety Renovation
PCL Construction completed all punch-list activities from the Architect of Record’s list. The final item awaiting completion is the threshold at the second floor entrance. The DSA Field Engineer also determined that additional truncated domes are required along the right edge of the driving ramp to ensure the safety of all users. Both items are anticipated to be completed in mid-February. Upon completion of these activities, the project will pursue DSA certification in February.