Project Overview

New signage will be installed on the building’s exterior to update the existing marquee signage located off Romneya Drive and the signage above the canopy at the Tower’s main entrance points. On the interior, directory and directional signage is planned to be updated next to elevators at each floor.

 

Status: Implementation

Project Estimate: Measure J=$2,737,431; Local=$59,000

Architect of Record: Westberg + White

Specialty Contractor: KYA Group, Inc.

Project Manager: Cora Baldovino

Program Management: MAAS Companies

Construction Start: November 2024

Construction Completion: Fall 2027

 

Upcoming Milestones

Interior Signage:

  • Signage Fabrication
  • Signage Installation

Develop Interior/Exterior Signage - Project Site

______________________________________________________________________

Implementation Pictures

 

Impacts and Closures

  • Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
  • Expect some noise, dust, and loss of use parking lot during construction

Emergency Contact: 

  • TBD

Q4 2026 Project Update

Develop Interior and Exterior Signage

October 

A Notice to Proceed with Construction was issued to KYA Group on September 9, after which, the installer started the process for signage procurement and fabrication. Shop drawings are in development. And, signage fabrication is planned to start November 22. Installation should follow in January 2027.