Project Overview

New signage will be installed on the building’s exterior to update the existing marquee signage located off Romneya Drive and the signage above the canopy at the Tower’s main entrance points. On the interior, directory and directional signage is planned to be updated next to elevators at each floor.

 

Status: Implementation

Project Estimate: Measure J=$1,337,431; Local=$59,000

Architect of Record: Westberg + White

Specialty Contractor: KYA Group, Inc.

Project Manager: Cora Baldovino

Program Management: MAAS Companies

Construction Start: November 2024

Construction Completion: Fall 2026

 

Upcoming Milestones

  • Scope of work Review and Cost Estimate Development
  • Bidding for Interior Signage Contractor Selection

Develop Interior/Exterior Signage - Project Site

______________________________________________________________________

Implementation Pictures

 

Impacts and Closures

  • Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
  • Expect some noise, dust, and loss of use parking lot during construction

Emergency Contact: 

  • TBD

Q4 2025 Project Update

Develop Interior and Exterior Signage

October

KYA Group, Inc., provided a $607,867 cost estimate for the remaining exterior work, including internal and external signage (B and C) and parking lot identifiers (D) on both sides of campus. Change Order No. 5 for a contract increase was approved on October 14, after which, the District executed and finalized the contract.

November

The signage drawings are under review with the Architect of Record (AOR). Upon the conclusion of the firm’s review, the signage will begin the process of fabrication, taking approximately eight weeks to complete. During that timeline, crews from KYA Group are anticipated to start establishing the signage base foundations inclusive of formwork, reinforcement bar and  electrical conduit placement for power, and concrete pouring. Once the signage arrives on-site, they will be set in place. Project completion for the exterior portion is anticipated to be achieved by  March 2026.

The Campus Project Team received direction from the North Orange Continuing Education (NOCE) - Anaheim Leadership to prioritize office and classroom modifications prior to proceeding with the interior signage portion of the project. Interior signage installation is anticipated to revisit the design in mid-2026, followed by fabrication and installation.