Project Overview

New signage will be installed on the building’s exterior to update the existing marquee signage located off Romneya Drive and the signage above the canopy at the Tower’s main entrance points. On the interior, directory and directional signage is planned to be updated next to elevators at each floor.

 

Status: Implementation

Project Estimate: Measure J=$1,496,431; Local=$59,000

Architect of Record: Westberg + White

Specialty Contractor: KYA Group, Inc.

Project Manager: Cora Baldovino

Program Management: MAAS Companies

Construction Start: November 2024

Construction Completion: Fall 2027

 

Upcoming Milestones

  • Exterior Signage Close-Out
  • Interior Signage Signage Implementation

Develop Interior/Exterior Signage - Project Site

______________________________________________________________________

Implementation Pictures

 

Impacts and Closures

  • Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
  • Expect some noise, dust, and loss of use parking lot during construction

Emergency Contact: 

  • TBD

Q2 2026 Project Update

Develop Interior and Exterior Signage

March 

The Campus Project Team is assessing interior signage recommendations presented by the Design Team based on the potential budget available to complete this portion of the project. Implementation for this scope of work is anticipated to start June 2026. 

April

Close-out is underway for the exterior portion of the project. A Notice of Completion is expected to be presented to the Board of Trustees in May for its consideration.

For the interior signage, KYA Group addressed the final budgetary cost by  completing value engineering to remove non-essentail items from the current scope of work. Additionally, small signage elements will be coordinated with APCO to minimize costs. Implementation is expected to start in the coming months.