Project Overview
New signage will be installed on the building’s exterior to update the existing marquee signage located off Romneya Drive and the signage above the canopy at the Tower’s main entrance points. On the interior, directory and directional signage is planned to be updated next to elevators at each floor.
Status: Implementation
Project Estimate: Measure J=$1,337,431; Local=$59,000
Architect of Record: Westberg + White
Specialty Contractor: KYA Group, Inc.
Project Manager: Cora Baldovino
Program Management: MAAS Companies
Construction Start: November 2024
Construction Completion: Fall 2026
Upcoming Milestones
- Scope of work Review and Cost Estimate Development
- Bidding for Interior Signage Contractor Selection
Develop Interior/Exterior Signage - Project Site
______________________________________________________________________
Implementation Pictures
Impacts and Closures
- Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
- Expect some noise, dust, and loss of use parking lot during construction
Emergency Contact:
- TBD
Q4 2025 Project Update
Develop Interior and Exterior Signage
October
KYA Group, Inc., provided a $607,867 cost estimate for the remaining exterior work, including internal and external signage (B and C) and parking lot identifiers (D) on both sides of campus. Change Order No. 5 for a contract increase was approved on October 14, after which, the District executed and finalized the contract.
November
The signage drawings are under review with the Architect of Record (AOR). Upon the conclusion of the firm’s review, the signage will begin the process of fabrication, taking approximately eight weeks to complete. During that timeline, crews from KYA Group are anticipated to start establishing the signage base foundations inclusive of formwork, reinforcement bar and electrical conduit placement for power, and concrete pouring. Once the signage arrives on-site, they will be set in place. Project completion for the exterior portion is anticipated to be achieved by March 2026.
The Campus Project Team received direction from the North Orange Continuing Education (NOCE) - Anaheim Leadership to prioritize office and classroom modifications prior to proceeding with the interior signage portion of the project. Interior signage installation is anticipated to revisit the design in mid-2026, followed by fabrication and installation.