Project Overview
New signage will be installed on the building’s exterior to update the existing marquee signage located off Romneya Drive and the signage above the canopy at the Tower’s main entrance points. On the interior, directory and directional signage is planned to be updated next to elevators at each floor.
Status: Implementation
Project Estimate: Measure J=$1,569,000; Local=$1,000,000
Architect of Record: Westberg White
Specialty Contractor: KYA Group, Inc.
Project Manager: Cora Baldovino
Program Management: MAAS Companies
Implementation Pictures
__________________________________________________________________________
Implementation Pictures
Q4 2024 Project Update
Develop Interior and Exterior Signage
Construction is anticipated to resume in January 2025 and is anticipated to take two months to complete. Work on the Romneya Drive marquee and the metal signage along the parapet wall along the parking deck will begin in January 2025.