Project Overview
New signage will be installed on the building’s exterior to update the existing marquee signage located off Romneya Drive and the signage above the canopy at the Tower’s main entrance points. On the interior, directory and directional signage is planned to be updated next to elevators at each floor.
Status: Implementation
Project Estimate: Measure J=$2,737,431; Local=$59,000
Architect of Record: Westberg + White
Specialty Contractor: KYA Group, Inc.
Project Manager: Cora Baldovino
Program Management: MAAS Companies
Construction Start: November 2024
Construction Completion: Fall 2027
Upcoming Milestones
- Exterior Signage Close-Out
- Interior Signage Signage Fabrication
Develop Interior/Exterior Signage - Project Site
______________________________________________________________________
Implementation Pictures
Impacts and Closures
- Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
- Expect some noise, dust, and loss of use parking lot during construction
Emergency Contact:
- TBD
Q2 2026 Project Update
Develop Interior and Exterior Signage
March
The Campus Project Team is assessing interior signage recommendations presented by the Design Team based on the potential budget available to complete this portion of the project. Implementation for this scope of work is anticipated to start June 2026.
April
Close-out is underway for the exterior portion of the project. A Notice of Completion is expected to be presented to the Board of Trustees in May for its consideration.
For the interior signage, KYA Group addressed the final budgetary cost by completing value engineering to remove non-essentail items from the current scope of work. Additionally, small signage elements will be coordinated with APCO to minimize costs. Implementation is expected to start in the coming months.
May
The project is undergoing close-out for the exterior portion of the scope of work, having achieved substantial completion in late April. Minor items are being addressed. Once resolved, a Notice of Completion is expected to be presented to the Board of Trustees in the coming months for its consideration. Once approved, the District will submit the Notice of Completion to the Orange County Registrar, triggering the 30-day count for release of retention for this portion of the project.
Signage coordinator, KYA Group, provided the Campus Project Team with the revised interior scope of work after taking steps to minimize expenses and meet the established budget at approximately $729K. The revised scope of work includes the addition of building and floor directories at the entrances, lobbies, and corridors along with wayfinding signage and artwork along the hallways. Architect of Record, Westberg+White, kicked-off Building User Group meetings on May 26 in coordination with the Campus Project Team. At that meeting, the scope of work was reviewed and solidified.
A Board Agenda Item is anticipated to be presented to the Board of Trustees in June to KYA Group for the implementation of the finalized interior scope of work prior to proceeding with fabrication and installation.