Project Overview

This greenspace will foster social gatherings in a grand quad with amphitheater seating for special events like commencement. Americans with Disabilities Act (ADA) improvements are included in the project scope of work for accessibility of all users.

Status: Design Development

Project Costs: Measure J=$1,839,000; Local=$2,999,537

Architects of Record: PBK Architects

General Contractor: TBD

Project Manager: Cora Baldovino

Program Management: MAAS Companies

Design Start: January 2025

Anticipated Design Completion: August 2025

Exterior Green Community Space Enhancement - Project SIte 

Exterior Green

Q3 2025 Project Update

July

By mid-July, the project achieved 85 percent Construction Documents (CDs). The CDs reached 95 percent on July 25 and DSA submittal took place on Monday July 28.

August

Back-check comments are anticipated to be received in September for the Design Team’s review and response from DSA. The project is anticipated to enter bidding an procurement for the selection of a general contractor in fall 2025.

September

The Design Team began developing the Construction Documents (CDs) that were finalized and submitted to the Campus Project Team for its review. The finalized submittal was made to DSA on July 28 for its review and approval.  Back-check comments are anticipated to be received in September for the Design Team’s consideration.

The project is anticipated to enter the bidding phase for the selection of a general contractor in fall 2025.