Project Overview

This greenspace will foster social gatherings in a grand quad with amphitheater seating for special events like commencement. Americans with Disabilities Act (ADA) improvements are included in the project scope of work for accessibility of all users.

Status: Construction

Project Costs: Measure J=$3,255,624; Local=$3,336,764

Architects of Record: PBK Architects

General Contractor: Horizons Construction 

Project Manager: Aaron Choi

Program Management: MAAS Companies

Construction Start: August 2026

Anticipated Construction Completion: Spring 2027

Exterior Green Community Space Enhancement - Project SIte 

Exterior Green

__________________________________________________________________________________________________

Construction Progress Photos

Upcoming Milestones: 

  • Site Surveying
  • Site Grading

Impacts and Closure:

  • Work is scheduled Monday - Friday from 7:00 AM to 4:30 PM
  • Expect some noise during construction

Emergency Contact:

  • MAAS Companies, Inc: (714) 808-4594

Q4 2026 Project Update

October 

Crews conducted demolition in September to remove shrubs before proceeding to the removal of light poles, concrete pavement, parking lot asphalt, and soil. The contractor then begin preparing site conditions for grading activities inclusive of surverying. By October, excavation began to build the concrete seating retaining wall, and the existing north wall at the driving ramp has been  cut to create two site entrances consisting of a staircase from the hillside and an accessible ramp around the site. Spoils testing and removal will precede grading, followed by storm drain installation ahead of anticipated inclement weather. Substantial completion is expected in mid-April, with a joint ribbon-cutting ceremony planned alongside the Design Interior/Exterior Signage project.