Project Overview
This greenspace will foster social gatherings in a grand quad with amphitheater seating for special events like commencement. Americans with Disabilities Act (ADA) improvements are included in the project scope of work for accessibility of all users.
Status: Construction
Project Costs: Measure J=$3,255,624; Local=$3,336,764
Architects of Record: PBK Architects
General Contractor: Horizons Construction
Project Manager: James McGrane
Program Management: MAAS Companies
Construction Start: August 2026
Anticipated Construction Completion: Spring 2027
Exterior Green Community Space Enhancement - Project SIte
__________________________________________________________________________________________________
Construction Progress Photos
Upcoming Milestones:
- Site Surveying
- Site Grading
Impacts and Closure:
- Work is scheduled Monday - Friday from 7:00 AM to 4:30 PM
- Expect some noise during construction
Emergency Contact:
- MAAS Companies, Inc: (714) 808-4594
Q3 2026 Project Update
September
The Campus Project Team completed the re-bidding process after receiving three bids by the June 16 deadline. After a period of review by the Construction and Project Management Team, Horizons Construction was selected as the lowest cost, most responsive, and responsible bidder. With Board of Trustees’ approval, the District executed the firm’s contract.
The Notice to Proceed with Construction was issued to Horizons Construction on August 17, followed by a construction kick-off meeting on August 19. The general contractor began mobilizing to the site, starting with the placement of perimeter fencing and later, the trailer on-site.
Utilities were safely disconnected before proceeding with site demolition. Demolition began with the removal of shrubs and green matter before proceeding to the removal of light poles, concrete pavement, parking lot asphalt, and soil. The contractor will then begin preparing site conditions for grading activities in the coming weeks.




