Project Overview
This greenspace will foster social gatherings in a grand quad with amphitheater seating for special events like commencement. Americans with Disabilities Act (ADA) improvements are included in the project scope of work for accessibility of all users.
Status: Construction
Project Costs: Measure J=$3,255,624; Local=$3,336,764
Architects of Record: PBK Architects
General Contractor: TBD
Project Manager: Cora Baldovino
Program Management: MAAS Companies
Construction Start: August 2026
Anticipated Construction Completion: Spring 2027
Exterior Green Community Space Enhancement - Project SIte
__________________________________________________________________________________________________
Construction Progress Photos
Upcoming Milestones:
Site Surveying
Site Grading
Impacts and Closure:
- Work is scheduled Monday - Friday from 7:00 AM to 4:30 PM
- Expect some noise during construction
Emergency Contact:
- MAAS Companies, Inc: (714)808-4594
Q3 2026 Project Update
July - August
The project is currently proceeding through the bidding phase. Following review of the original bid process and consultation with District legal counsel, the District determined that additional clarification regarding project phasing and sequencing should be incorporated into the bid documents to provide clearer direction to bidders. As a result, a request to cancel the bids was submitted to the Board of Trustees for consideration on May 26.
The revised bid documents were issued to the pre-qualified bidders on May 29. An optional site walk took place on June 2. Bids from the three prequalified were received on June 16. The Campus Project Team concluded the re-bidding process after three bids were received by the allotted deadline. Horizons Construction was selected as the lowest cost, most responsive and responsible general contractor. A Board Agenda Item for the selected firm was presented to the Board of Trustees on July 28. With the Board’s approval, the District executed the firm’s contract. The Notice to Proceed with Construction was issued to the contractor on August 17 followed by mobilization activities. Site perimeter fencing will be set in place along with the contractor’s trailer in the laydown area by the warehouse. Temporary utilities will be established before the existing utilities are disconnected and tied off. Site demolition will follow along with grading activities. The project is estimated to last nine months.




