Project Overview
This greenspace will foster social gatherings in a grand quad with amphitheater seating for special events like commencement. Americans with Disabilities Act (ADA) improvements are included in the project scope of work for accessibility of all users.
Status: Construction
Project Costs: Measure J=$3,255,624; Local=$3,336,764
Architects of Record: PBK Architects
General Contractor: Horizons Construction
Project Manager: Aaron Choi
Program Management: MAAS Companies
Construction Start: August 2026
Anticipated Construction Completion: Spring 2027
Exterior Green Community Space Enhancement - Project SIte
__________________________________________________________________________________________________
Construction Progress Photos
Upcoming Milestones:
- Site Surveying
- Site Grading
Impacts and Closure:
- Work is scheduled Monday - Friday from 7:00 AM to 4:30 PM
- Expect some noise during construction
Emergency Contact:
- MAAS Companies, Inc: (714) 808-4594
Q4 2026 Project Update
October
Crews conducted demolition in September to remove shrubs before proceeding to the removal of light poles, concrete pavement, parking lot asphalt, and soil. The contractor then begin preparing site conditions for grading activities inclusive of surverying. By October, excavation began to build the concrete seating retaining wall, and the existing north wall at the driving ramp has been cut to create two site entrances consisting of a staircase from the hillside and an accessible ramp around the site. Spoils testing and removal will precede grading, followed by storm drain installation ahead of anticipated inclement weather. Substantial completion is expected in mid-April, with a joint ribbon-cutting ceremony planned alongside the Design Interior/Exterior Signage project.




