Scope:
Projects related to the upgrade of existing campus mass communication and security systems. Installation of modified entry doors at Building 9 Business Education.
Status:
This project was activated in April 2018. Installation of the new doors at Building 9 Business Education was completed in early January 2019.
Project Estimate:
$50,671
Campus Project Manager:
Philip Fleming
District Director, Facilities Planning & Construction:
Richard Williams
Program Management:
MAAS Companies