Project Overview

The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.

 

Status: Construction

Project Costs: Measure J=$6,399,604; Local=$13,788,127

Architect of Record: Roesling Nakamura Terada Architects, Inc.

General Contractor: BN Builder, Inc.

Project Manager: John Erickson

Program Management: MAAS Companies

Construction Start: October 2023

Anticipated Completion: April 2025

New M&O Building - Project Site

__________________________________________________________________________

Construction Progress Pictures

Upcoming Milestones

  • Interior Finishes
  • Roofing Activities
  • Exterior Facade Actvities
  • Hardscape, Landscaping, and Striping

Impacts and Closures

  • Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
  • Expect some noise during construction

Emergency Contact

  • Victor Vasquez (Lead Superintendent): (714) 732-4730
  • Rosendo Pantoja (Superintendent): (714) 352-1926

Q1 2025 Project Update

New Maintenance & Operations Building

Crews completed roofing activities and are nearing completion of the exterior lathing, making the façade ready for plaster. The exterior windows will be completed in the third week of January. Interior overhead, and in-wall mechanical, electrical, and plumbing (MEPs) have concluded. Drywall installation achieved 75 percent completion. Interior electrical gear and rooftop equipment were installed in the week of January 13. BN Builders is preparing for building energizing on February 14. Coordination is underway for a temporary shutdown over President’s Day weekend to support commissioning activities.