Project Overview
The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.
Status: Close-Out
Project Costs: Measure J=$6,399,604; Local=$13,717,050
Architect of Record: Roesling Nakamura Terada Architects, Inc.
General Contractor: BN Builders, Inc.
Project Manager: John Erickson
Program Management: MAAS Companies
Construction Start: October 2023
Construction Completion: June 2025
New M&O Building - Project Site
__________________________________________________________________________
Construction Progress Pictures
Milestones
- Financial Close-Out
Impacts and Closures
- Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
- Expect some noise during construction
Emergency Contact
- Victor Vasquez (Lead Superintendent): (714) 732-4730
- Rosendo Pantoja (Superintendent): (714) 352-1926
Q3 2025 Project Update
New Maintenance & Operations Building
July
Moving activities took place in the third week of July. The vehicular gate was installed in the same week.
Close-out activities are proceeding starting with the collection of as-built drawings, submittals, warranties and manuals. Trainings also are underway with Campus Facilities and staff prior to the issuance of the Notice of Completion in the coming months. The vehicular gate was installed in the third week of July. The project then achieved substantial completion in mid-July.
August
Minor work is being addressed to resolve comments received by the DSA field engineer on pendant lights installed in the building. Additionally, the building’s access control is being finalized in the third week of August.
Moving activities are taking place in August including the relocation of personnel, furniture, and equipment to the site. To commemorate this momentous occasion, Campus Leadership is anticipated to hold an opening ceremony in mid-September with members of the Citizens’ Oversight Committee in attendance.