Project Overview
The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.
Status: Construction
Project Costs: Measure J=$6,399,604; Local=$13,717,050
Architect of Record: Roesling Nakamura Terada Architects, Inc.
General Contractor: BN Builders, Inc.
Project Manager: John Erickson
Program Management: MAAS Companies
Construction Start: October 2023
Anticipated Completion: April 2025
New M&O Building - Project Site
__________________________________________________________________________
Construction Progress Pictures
Upcoming Milestones
- Interior Finishes
- Painting Activities
- Hardscape, Landscaping, and Striping
Impacts and Closures
- Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
- Expect some noise during construction
Emergency Contact
- Victor Vasquez (Lead Superintendent): (714) 732-4730
- Rosendo Pantoja (Superintendent): (714) 352-1926
Q1 2025 Project Update
New Maintenance & Operations Building
By early March, scaffolding was removed from the building exterior after the conclusion of façade activities to allow for work on the utilities and hardscape to proceed. Gutters and other exterior flashing have been installed, with clay roof tiles scheduled for installation in the third week of the month.
Inside the structure, acoustical ceiling tile installation is ongoing. Doors and hardware are scheduled to be set in place in the coming weeks, and ceiling light activities began at the start of the month. Work on the elevators is ongoing and concluded by the second week of the month.
Restroom tiling is progressing followed by ceiling installation. Once the ceiling tiles are in place, flooring and specialty equipment installation will follow in the third week of March.
The intermediate distribution frame rooms that distribute network connectivity from the main building distribution frame to each floor will be completed in the first week of the month.
Ceiling grids, acoustical tile installation, and lighting, are progressing in the maintenance shop and golf cart storage areas.
All other finishes began in March and are scheduled to end in April. Sidewalk activities began starting with site grading in early March.