Project Overview
The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.
Status: Construction
Project Costs: Measure J=$6,399,604; Local=$13,788,127
Architect of Record: Roesling Nakamura Terada Architects, Inc.
General Contractor: BN Builder, Inc.
Project Manager: John Erickson
Program Management: MAAS Companies
Construction Start: October 2023
Anticipated Completion: April 2025
New M&O Building - Project Site
__________________________________________________________________________
Construction Progress Pictures
Upcoming Milestones
- Interior Finishes
- Roofing Activities
- Exterior Facade Actvities
- Hardscape, Landscaping, and Striping
Impacts and Closures
- Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
- Expect some noise during construction
Emergency Contact
- Victor Vasquez (Lead Superintendent): (714) 732-4730
- Rosendo Pantoja (Superintendent): (714) 352-1926
Q1 2025 Project Update
New Maintenance & Operations Building
Crews completed roofing activities and are nearing completion of the exterior lathing, making the façade ready for plaster. The exterior windows will be completed in the third week of January. Interior overhead, and in-wall mechanical, electrical, and plumbing (MEPs) have concluded. Drywall installation achieved 75 percent completion. Interior electrical gear and rooftop equipment were installed in the week of January 13. BN Builders is preparing for building energizing on February 14. Coordination is underway for a temporary shutdown over President’s Day weekend to support commissioning activities.