Project Overview

The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.

 

Status: Close-Out

Project Costs: Measure J=$6,399,604; Local=$13,717,050

Architect of Record: Roesling Nakamura Terada Architects, Inc.

General Contractor: BN Builders, Inc.

Project Manager: John Erickson

Program Management: MAAS Companies

Construction Start: October 2023

Construction Completion: June 2025

New M&O Building - Project Site

__________________________________________________________________________

Construction Progress Pictures

Milestones

  • Financial Close-Out

Impacts and Closures

  • Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
  • Expect some noise during construction

Emergency Contact

  • Victor Vasquez (Lead Superintendent): (714) 732-4730
  • Rosendo Pantoja (Superintendent): (714) 352-1926

Q3 2025 Project Update

New Maintenance & Operations Building

July 

Moving activities took place in the third week of July. The vehicular gate was installed in the same week.

Close-out activities are proceeding starting with the collection of as-built drawings, submittals, warranties and manuals. Trainings also are underway with Campus Facilities and staff prior to the issuance of the Notice of Completion in the coming months. The vehicular gate was installed in the third week of July. The project then achieved substantial completion in mid-July.

August

Minor work is being addressed to resolve comments received by the DSA field engineer on pendant lights installed in the building. Additionally, the building’s access control is being finalized in the third week of August.

Moving activities are taking place in August including the relocation of personnel, furniture, and equipment to the site. To commemorate this momentous occasion, Campus Leadership is anticipated to hold an opening ceremony in mid-September with members of the Citizens’ Oversight Committee in attendance.