Project Overview

The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.

 

Status: Construction

Project Costs: Measure J=$6,399,604; Local=$11,121,135

Architect of Record: Roesling Nakamura Terada Architects, Inc.

General Contractor: BN Builder, Inc.

Project Manager: Oscar Saghieh

Program Management: MAAS Companies

Anticipated Completion: Winter 2024

New M&O Building - Project Site

__________________________________________________________________________

Construction Progress Pictures

Upcoming Milestones:

  • Slab on grade activities

 

Impacts and Closure

  • Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
  • Expect some noise during construction

Emergency Contact:

  • Victor Vasquez (Lead Superintendent)
    • 714 732 4730
  • Rosendo Pantoja (Superintendent)
    • 714 352 1926

Q2 2024 Project Update

New Maintenance & Operations Building

Structural steel installation began on May 21 for the first floor and concluded in early June. Work continued on Concrete Masonry Unit (CMU) wall assembly. Bricks are now in place to form the perimeter of the building.  Crews have completed the fifth, sixth, and seventh lifts; work on the eighth and ninth lifts are underway. CMU activities are anticipated to conclude at the end of June. Following completion, scaffolding will be removed from the building. At the same time, roof embeds to anchor the steel to the CMU walls will be installed, alongside grouting work. Electrical activities are underway and raceway conduits are being placed into the walls.