Project Overview
The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.
Status: Construction
Project Costs: Measure J=$6,399,604; Local=$13,717,050
Architect of Record: Roesling Nakamura Terada Architects, Inc.
General Contractor: BN Builders, Inc.
Project Manager: John Erickson
Program Management: MAAS Companies
Construction Start: October 2023
Anticipated Completion: April 2025
New M&O Building - Project Site
__________________________________________________________________________
Construction Progress Pictures
Upcoming Milestones
- Interior Finishes
- Painting Activities
- Hardscape, Landscaping, and Striping
Impacts and Closures
- Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
- Expect some noise during construction
Emergency Contact
- Victor Vasquez (Lead Superintendent): (714) 732-4730
- Rosendo Pantoja (Superintendent): (714) 352-1926
Q1 2025 Project Update
New Maintenance & Operations Building
The exterior of the building is progressing, with both sloped and flat roofs having been completed. The building façade underwent a brown coat application that was allowed to cure in early February. This step preceded the application of the final stucco finish coat, which was scheduled for February 10th. Clay roof tiles were planned to commence installation on the same day.
Exterior door deliveries began in early February, and underwent installation promptly upon their arrival. The current date to power-on the building is scheduled for February 24.
Inside the building, equipment rack installation and electrical wiring continued in the intermediate distribution frame and building distribution frame rooms. Drywall installation concluded on the second floor; crews started painting and priming in the completed areas. Ceiling installation progressed, with lighting activities marking its conclusion soon after. Moisture testing was planned in preparation for flooring installation, set for late February. Meanwhile, elevator installation continued and expected to be completed by March.