Project Overview
The New Maintenance and Operations (M&O) Building will centralize all services into a single building located on the Main Campus. The building will include trade-specific workshops for maintenance, grounds, facilities, and custodial personnel while improving response time and efficiencies by locating the building on the Main Campus adjacent to the central plant.
Status: Close-Out
Project Costs: Measure J=$6,399,604; Local=$13,717,050
Architect of Record: Roesling Nakamura Terada Architects, Inc.
General Contractor: BN Builders, Inc.
Project Manager: John Erickson
Program Management: MAAS Companies
Construction Start: October 2023
Construction Completion: June 2025
New M&O Building - Project Site
__________________________________________________________________________
Construction Progress Pictures
Milestones
- Financial Close-Out
Impacts and Closures
- Working is scheduled Monday - Friday From 7:30 AM to 5:30 PM
- Expect some noise during construction
Emergency Contact
- Victor Vasquez (Lead Superintendent): (714) 732-4730
- Rosendo Pantoja (Superintendent): (714) 352-1926
Q2 2026 Project Update
New Maintenance & Operations Building
March - June
Change Order No. 2 was presented to the Board of Trustees along with the Notice of Completion that were approved. The final item required by the DSA Field Engineer is the uninterrupted power supply to provide power in emergency situations to the building automated doors. The items were ordered, installed, and completed by May 1;. Project sign-off is expected to be achieved by the Inspector of Record on projects in the following weeks. The remaining work will be signed off by DSA to achieve final completion.







