Project Overview

This project addresses the demand for enrollment in the Performing Arts programs by constructing a new complex that will combine music, drama, theater arts, and communication programs into a single facility. The new building will replace outdated facilities with electrical deficiencies and outmoded configurations. The new structure will take advantage of the potential use of commonly required spaces to improve overall utilization and flexible spaces that help programs in meeting higher demands anticipated in the near future.

 

Status: Construction

Project Costs: Measure J=$92,005,166; Local=$163,859; Capital Outlay=$43,787,000

Architect of Record: Perkins Eastman  Architects DPC

Project Manager: John Erickson

General Contractor: SJ Amoroso

Construction Manager: Kitchell/CEM, Inc. 

Program Management: MAAS Companies

Construction Start: May 2025

Anticipated Construction Completion: Summer 2028

 

 

Future Site For New Performing Arts Complex

__________________________________________________________________

Construction Progress Photos

Upcoming Milestones

  • CMU Wall Installation
  • Foundation Activities at Orchestra Pit

Impacts and Closures

  • Working is scheduled Monday - Friday from 7:00 AM - 4:30 PM
  • Expect some noise, dust, and loss of use parking lot during construction

Emergency Contact:

  • Mike McNally: 714-433-2326

Q4 2026 Project Update

New Performing Arts Complex

October 

Throughout October, foundation work advanced from caisson and pier drilling toward planned grade-beam and pier-cap construction in the Auditorium and East Building areas. By October 28, the remaining caisson, pile-cap, and stair work was sequenced to support Auditorium construction, with additional excavation planned for the following week.

In the Basement, underground utility work progressed alongside preparations for the concrete slab pour on November 23. Gravel placement in the classroom-building at the Basement was nearly complete; vapor barrier installation will follow in early November, followed by reinforcement and final slab preparation.

At the West Building, work expanded from exterior and interior framing to specialized roof framing, overhead utility rough-in, and insulation. By late October, the mezzanine was complete and awaiting drywall, and wall assemblies were being insulated before installation. Weather, roofing delays, and the unresolved gutter mock-up continued to affect building enclosure work, while drywall installation was planned for accessible areas.

Design and submittal coordination continued in parallel with field construction. The October 7 update scheduled the Orchestra Shell submission to DSA to begin October 26, although completion was not confirmed in the subsequent update. By October 28, GFRC CAD files had been received, and the design team was coordinating revisions, the deferred geotechnical submittal, shop drawings, and related CCD processing.