Project Overview

This project will restore the East Parking Lot to its original use after dismantling the temporary classrooms that were in operation for the duration of the Anaheim Tower First Floor/Life Safety Renovation project. 

Status: Design - Construction Documents 

Project Costs: Measure J=$1,622,560

Architect of Record: PBK Architects 

Project Manager: Cora Baldovino

General Contractor: TBD

Construction Manager: TBD

Program Management: MAAS Companies

Design Start: April 2025

Anticipated Design Completion: August 2025

Restore East Parking Lot - Project Site

Q3 2025 Project Update

July 

The Design Team is addressing the Construction Documents (CDs) and are expected to achieve 95 percent CDs July 18. A DSA submittal is expected to be made to the state architect agency in the coming weeks.