Project Overview

This project will restore the East Parking Lot to its original use after dismantling the temporary classrooms that were in operation for the duration of the Anaheim Tower First Floor/Life Safety Renovation project. 

Status: Construction

Project Costs: Measure J=$2,211,673

Architect of Record: PBK Architects 

Project Manager: Cora Baldovino

General Contractor: PaveWest

Construction Manager: TBD

Program Management: MAAS Companies

Construction Start: January 2026

Construction Completion: April 2026

Restore East Parking Lot - Project Site

Q1 2026 Project Update

January 

On January 6, 2026, the project broke ground with the selected general contractor, PaveWest, following their approval by the Board of Trustees in mid-December.

A Notice to Proceed with with construction was issued on the aforementioned date, after which, PaveWest began mobilization activities and site demolition that continued until third week of January.

Crews then proceeded to start grading activities to ensure a leveled surface prior to proceeding with asphalt paving. Construction Field Instructions have been issued to facilitate the addition of a fire lane, light poles, and perform required electrical repairs for improved safety in the area,