Project Overview
This project will restore the East Parking Lot to its original use after dismantling the temporary classrooms that were in operation for the duration of the Anaheim Tower First Floor/Life Safety Renovation project.
Status: Design - Construction Documents
Project Costs: Measure J=$1,622,560
Architect of Record: PBK Architects
Project Manager: Cora Baldovino
General Contractor: TBD
Construction Manager: TBD
Program Management: MAAS Companies
Design Start: April 2025
Anticipated Design Completion: August 2025
Restore East Parking Lot - Project Site

Q3 2025 Project Update
July
The Design Team is addressing the Construction Documents (CDs) and are expected to achieve 95 percent CDs July 18. A DSA submittal is expected to be made to the state architect agency in the coming weeks.
August
The Design Team began developing the Construction Documents (CDs) that were finalized and submitted to the Campus Project Team for its review. The finalized submittal was made to DSA on July 24 for its review and approval. Upon the conclusion of these activities, the project will enter the bidding phase, allowing for the start of the general contractor selection process.