Project Overview

This project will restore the East Parking Lot to its original use after dismantling the temporary classrooms that were in operation for the duration of the Anaheim Tower First Floor/Life Safety Renovation project. 

Status: Bidding 

Project Costs: Measure J=$1,622,560

Architect of Record: PBK Architects 

Project Manager: Cora Baldovino

General Contractor: TBD

Construction Manager: TBD

Program Management: MAAS Companies

Design Start: April 2025

Anticipated Design Completion: August 2025

Restore East Parking Lot - Project Site

Q4 2025 Project Update

October

The previously submitted Construction Documents (CDs) remained under review in early September. The Design Team addressed the back-check comments provided by DSA. Subsequently, DSA approval was granted, permitting the commencement of the bidding phase for the selection of a general contractor.

In collaboration with the District, the Campus Project Team prepared and electronically issued the bid announcement on October 13. All proposals are to be submitted by Monday, November 10. Following the evaluation process, the Campus Project Team will present the recommended contractor as a Board Agenda Item for consideration and approval by the Board of Trustees at the December meeting.