Project Overview
This project will restore the East Parking Lot to its original use after dismantling the temporary classrooms that were in operation for the duration of the Anaheim Tower First Floor/Life Safety Renovation project.
Status: Construction
Project Costs: Measure J=$2,211,673
Architect of Record: PBK Architects
Project Manager: Cora Baldovino
General Contractor: PaveWest
Construction Manager: TBD
Program Management: MAAS Companies
Construction Start: January 2026
Construction Completion: April 2026
Restore East Parking Lot - Project Site
Q1 2026 Project Update
January
On January 6, 2026, the project broke ground with the selected general contractor, PaveWest, following their approval by the Board of Trustees in mid-December.
A Notice to Proceed with with construction was issued on the aforementioned date, after which, PaveWest began mobilization activities and site demolition that continued until third week of January.
Crews then proceeded to start grading activities to ensure a leveled surface prior to proceeding with asphalt paving. Construction Field Instructions have been issued to facilitate the addition of a fire lane, light poles, and perform required electrical repairs for improved safety in the area,




