Project Overview
This project will restore the East Parking Lot to its original use after dismantling the temporary classrooms that were in operation for the duration of the Anaheim Tower First Floor/Life Safety Renovation project.
Status: Construction
Project Costs: Measure J=$2,521,574
Architect of Record: PBK Architects
Project Manager: Cora Baldovino
General Contractor: PaveWest
Construction Manager: TBD
Program Management: MAAS Companies
Construction Start: January 2026
Construction Completion: April 2026
Restore East Parking Lot - Project Site
Q2 2026 Project Update
March - June
Crews have laid curbs to form the future parking stalls. Conduit installation was completed along with formwork to form the bases of the future lights in the parking lot. Asphalt paving took place in the final week of March, followed by a short curing period. Construction Field Instructions have been issued to facilitate the addition of light poles and electrical repairs for improved safety in the area. Long lead items non-critical to the completion of the project are being tracked by the Campus Project Team and general contractor.




