Project Overview

This project will restore the East Parking Lot to its original use after dismantling the temporary classrooms that were in operation for the duration of the Anaheim Tower First Floor/Life Safety Renovation project. 

Status: Close-Out

Project Costs: Measure J=$2,233,876

Architect of Record: PBK Architects 

Project Manager: Cora Baldovino

General Contractor: PaveWest

Construction Manager:  N/A

Program Management: MAAS Companies

Construction Start: January 2026

Construction Completion: April 2026

Restore East Parking Lot - Project Site

Q3 2026 Project Update

September

As the project nears final completion, PaveWest addressed concrete repairs at the electrical vehicle panels. By early August, minor improvements were made at the Anaheim Tower’s east entrance to support access to the East Parking Lot while the Exterior Green Community Space Enhancement project proceeds. The parking lot reopened in the second week of August.
The Notice of Completion was filed with the Orange County Clerk-Recorder triggering the countdown to release the final retention to PaveWest. Once financial and document close-out is completed, and certified by DSA, the project will be complete.