Project Overview

This project will restore the East Parking Lot to its original use after dismantling the temporary classrooms that were in operation for the duration of the Anaheim Tower First Floor/Life Safety Renovation project. 

Status: Close-Out

Project Costs: Measure J=$2,233,876

Architect of Record: PBK Architects 

Project Manager: Cora Baldovino

General Contractor: PaveWest

Construction Manager:  N/A

Program Management: MAAS Companies

Construction Start: January 2026

Construction Completion: April 2026

Restore East Parking Lot - Project Site

Q4 2026 Project Update

October

The Notice of Completion was filed with the Orange County Clerk-Recorder triggering the countdown to release the final retention to PaveWest. Once financial and document close-out is completed, and certified by DSA, the project will be complete.