Project Overview
A total renovation of Building 300, including seismic enhancements and historic consideration are planned for Building 300. Upon completion, the building will contain general classrooms, dean and faculty offices, and shared laboratories, and improved foundations for a safer built environment.
Status: Construction
Project Costs: Measure J=$22,982,000; State Capital Outlay=$11,272,621; Local=$9,240
Architect of Record: Westberg White
Project Manager: Oscar Saghieh
General Contractor: Icon West
Construction Manager: Simpson & Simpson
Program Management: MAAS Companies
Construction start: May 2024
Anticipate Completion: Winter 2026
Upcoming Milestones
- Basement Floor Demolition
- Underground conduits
- Building Exterior and Piling Work
- Rebar Work for Slab-On-Grade
Renovate Building 300 - Project Site
Future Site For Building 300
Impacts and Closure:
- Working is scheduled Monday - Friday from 7:00 AM to 5:30 PM
- Expect some noise during construction
Emergency Contact:
- Ramon Calma - Superintendent
- 310 720 1196
- Ramon@icon-west.com
- Mike Khan - Project Manager
- 213 545 4759
- Mike@icon-west.com
- Brandan Chaves - Project Engineer
- 213 7182728
- brandanc@icon-west.com
Q4 2024 Project Update
The fiber reinforced polymer submittal was given to DSA for review on November 19 as part of the seismic retrofit for the upper levels of the building. The state agency is anticipated to provide its approval in the coming weeks, after which work will begin and finish in February 2025. Cast-in-drill-hole activities around the building perimeter are complete, and the micropile installation for the seismic retrofit is ongoing.
DSA has approved a Construction Change Directive to allow for 10 micropiles to be drilled in areas where there are challenges in achieving standard clearance for the equipment. Pile cap activities will commence after micropile driving ends in January 2025.
The rough-in for heating, ventilation, cooling, and plumbing on the second and first floors has been addressed. Interior plaster stabilization is finished, and historic window restoration is expected to conclude this month.
The project is anticipated to reach substantial completion by mid-January 2026 and will conclude in February 2026.