Project Overview

A total renovation of Building 300, including seismic enhancements and historic consideration are planned for Building 300. Upon completion, the building will contain general classrooms, dean and faculty offices, and shared laboratories, and improved foundations for a safer built environment.

 

Status: Construction

Project Costs: Measure J=$22,982,000; State Capital Outlay=$11,272,621; Local=$9,240

Architect of Record: Westberg White

Project Manager: John Erickson

General Contractor: Icon West

Construction Manager: Simpson & Simpson

Program Management: MAAS Companies

Construction start: May 2024

Anticipate Completion: Winter 2026

Upcoming Milestones

  • Excavation for Underground Conduits
  • Staircase reconstruction
  • Interior Wall Framing

Renovate Building 300 - Project Site

2025_01_03_Renovate 300_Aerial Image

Future Site For Building 300

Impacts and Closure:

  • Working is scheduled Monday - Friday from 7:00 AM to 5:30 PM
  • Expect some noise during construction

Emergency Contact:

  • Ramon Calma - Superintendent
    • 310 720 1196
    • Ramon@icon-west.com
  • Mike Khan - Project Manager
    • 213 545 4759
    • Mike@icon-west.com
  • Brandan Chaves - Project Engineer
    • 213 7182728
    • brandanc@icon-west.com

Q1 2025 Project Update

By January 8, micropiles for all areas were completed including the micropiles at all four corners. Crews are addressing pile caps along the middle corridor. The fiber reinforced polymer (FRP) submittal was approved by DSA in the first week of January. General contractor, Icon West, is installing the FRP material on the underside of the roof and preparing the second-floor for concrete slab application.

The project is anticipated to reach substantial completion by mid-January 2026 and will conclude in February 2026.