Project Overview
A total renovation of Building 300, including seismic enhancements and historic consideration are planned for Building 300. Upon completion, the building will contain general classrooms, dean and faculty offices, and shared laboratories, and improved foundations for a safer built environment.
Status: Construction
Project Costs: Measure J=$22,982,000; State Capital Outlay=$11,272,621; Local=$9,240
Architect of Record: Westberg White
Project Manager: John Erickson
General Contractor: Icon West
Construction Manager: Simpson & Simpson
Program Management: MAAS Companies
Construction start: May 2024
Anticipate Completion: Winter 2026
Upcoming Milestones
- Excavation for Underground Conduits
- Staircase reconstruction
- Interior Wall Framing
Renovate Building 300 - Project Site

Future Site For Building 300
Impacts and Closure:
- Working is scheduled Monday - Friday from 7:00 AM to 5:30 PM
- Expect some noise during construction
Emergency Contact:
- Ramon Calma - Superintendent
- 310 720 1196
- Ramon@icon-west.com
- Mike Khan - Project Manager
- 213 545 4759
- Mike@icon-west.com
- Brandan Chaves - Project Engineer
- 213 7182728
- brandanc@icon-west.com
Q1 2025 Project Update
By January 8, micropiles for all areas were completed including the micropiles at all four corners. Crews are addressing pile caps along the middle corridor. The fiber reinforced polymer (FRP) submittal was approved by DSA in the first week of January. General contractor, Icon West, is installing the FRP material on the underside of the roof and preparing the second-floor for concrete slab application.
The project is anticipated to reach substantial completion by mid-January 2026 and will conclude in February 2026.