Project Overview

A total renovation of Building 300, including seismic enhancements and historic consideration are planned for Building 300. Upon completion, the building will contain general classrooms, dean and faculty offices, and shared laboratories, and improved foundations for a safer built environment.

 

Status: Construction

Project Costs: Measure J=$22,982,000; State Capital Outlay=$11,272,621; Local=$9,240

Architect of Record: Westberg White

Project Manager: John Erickson

General Contractor: Icon West

Construction Manager: Simpson & Simpson

Program Management: MAAS Companies

Construction start: May 2024

Anticipate Construction Completion: Winter 2026

Upcoming Milestones

  • Excavation for Underground Conduits
  • Staircase reconstruction
  • Interior Wall Framing

Renovate Building 300 - Project Site

2025_01_03_Renovate 300_Aerial Image

Future Site For Building 300

Impacts and Closure:

  • Working is scheduled Monday - Friday from 7:00 AM to 5:30 PM
  • Expect some noise during construction

Emergency Contact:

  • Ramon Calma - Superintendent
    • 310 720 1196
    • Ramon@icon-west.com
  • Mike Khan - Project Manager
    • 213 545 4759
    • Mike@icon-west.com
  • Brandan Chaves - Project Engineer
    • 213 7182728
    • brandanc@icon-west.com

Q2 2025 Project Update

April

The fiber reinforced polymer (FRP) on the second-floor neared completion by the start of April and was completed in the second to last week of the month. Crews then performed rough-in mechanical, electrical, and plumbing (MEP) work after its conclusion, with 20 percent remaining by the end of the month. Drywall and insulation installation is scheduled for May, with deliveries and subsequent installation expected in the first week of the month. Crews are continuing to address wall framing on the same floor and expected to finish by the third week of the month.

Following the completion of activities on the second floor, crews will proceed with FRP work on the first floor and basement, aiming for completion by early May. Installation of ductwork and supports on the first floor began in early April. Wall framing began mid-April, with activities expected to conclude by mid-May. Mechanical, electrical, and plumbing (MEP) rough-in work will follow framing, and continue until mid-June. Crews will then begin addressing drywall hanging in mid-June. The campus IT team will be on-site at the beginning of the third week of May to review wall ports and outlets. Hazardous materials abatement at the window wooden frames is currently underway and will continue until mid-May.

Preparations for the upcoming delivery of the air handling unit, heat exchanger, and pumps are in progress. Coordination for the cold-water line is planned to minimize any potential impacts on campus operations in the coming weeks.

The west staircase and wall are being rebuilt, with reinforcement bars and formwork being set in place. Initial concrete pours for footings started in the second week of April, followed by additional pours in mid-April. Crews are expected to start work on the north and south staircases in late April, pending approval of an outstanding construction change directive (CCD) with DSA. The installation of the electrical substation is underway. Site work is anticipated to start near the end of April.

In the basement, ductwork installation is expected to be completed by the end of the third week of April, with ductwork seismic supports delivery scheduled. Switch gear installation is expected to start at the end of April.

May

On the second floor of the building’s interior, drywall hanging is progressing; this portion of the scope of work is planned to conclude in the third week of the month. The second layer is expected to be applied in June. Insulation activities are planned to be addressed in mid-May. The walls are expected to be closed by the end of the month, with drywall taping, sanding, and primer application scheduled for June. Cement boards arrived on site in mid-May, paving the way for final tiling work. Fire caulking and sealant will commence throughout the second level in June and ceiling grids are anticipated to be installed in July.

Hallway ceiling framing is advancing, with work on the roof soffits set to begin at the end of the first week of May, followed by wall and MEP pipe insulation. Hydronic line installation began in the first week of this month and concluded by the end of the same week. Inspections will start once piping on both floors is in place. Overhead MEP work is expected to be completed concurrently with drywall hanging.

On the first floor, the completion of the FRP installation is expected in the third week of the month. Wall framing, backing, and door frames are also progressing, followed by rough-in MEP and placement of data infrastructure. The Campus Academic Computing Technologies (ACT) team is anticipated to visit the site in late May to review receptacle locations. Drywall hanging on the first floor will begin at the start of June. Overhead seismic bracing has been completed.

Preparations for the new sidewalk are underway. Work on underground plumbing and irrigation is expected to start by the end of May, with chilled water line underground installation proceeding in early June near Building 1300.

In the basement, equipment installation and bracing continued into the third week of May. The electrical substation has been set and is awaiting construction change directive responses prior to its completion.

Grading is progressing in preparation for the placement of reinforcement bars and concrete pours for the sidewalks.

Trenching for underground plumbing began in the last week of May for irrigation lines and other plumbing adjacent to the building. The new chilled water line connections will start in the first week of June with tie–into the existing utilities by the third week of June.