Project Overview

This project intends to address deficiencies to the existing facilities and associated infrastructure for the campus athletics field department.

 

Status: Pre-Bidding

Project Costs: Measure J= $7,000,000

Architects of Record: Westberg White Architects

General Contractor: TBD

Project Manager: Joel Gonzalez

Program Management: MAAS Companies

Bidding Start: June 2026

Bidding Completion: August 2026 

Future Site For Athletic Field Improvements

Untitled

Q2 2026 Project Update

April - June

In early March, the Campus Project Team submitted the soils report to the California Geological Survey (CGS) as part of DSA requirements for final Construction Documents’ approval. After a period of review, CGS provided its agreement with the report on April 22; a notification was sent to the Campus Project Team by letter. DSA then provided its final stamp of approval to the Construction Documents on April 23.

The project is now able to proceed with the bidding phase for general contractor selection. The bid documents are anticipated to be finalized and released by District Purchasing to the electronic portal on PlanetBids by mid-June. Interested firms will be invited to attend a mandatory job walk and to participate in the request-for-information process. Once all bids are received in late August, the most responsible, responsive, and lowest-cost general contractor will be selected to oversee the construction of this project. The Campus Project Team will then present a Board Agenda Item to the Board of Trustees for its consideration in early September. A Notice to Proceed with Construction is planned to be presented to the selected firm in September.

Fullerton Leadership is actively solidifying an alternative venue for the women’s softball team to host their 2026-27 season games before the start of construction in early September.