Project Overview
Located at the intersections of Chapman Avenue and Newell Street, the Student Support Center will be home to an array of student services vital to their success including the Campus Veterans’ Resource Center, Student Wellness Center (both medical and behavioral health), the Campus Food Bank, Umoja Community Program, Extended Opportunity Programs and Services (EOPS), CalWORKS, Cooperative Agencies Resources for Education (CARE)/Foster Youth Success Initiative (FYSI), a Multi-Cultural Center, and 2 instructional classrooms. In addition, there will be support functions including shared community storage, a department-wide copy, and a breakroom as well as a lactation room for the benefit of all users.
Status: Close-Out
Project Costs: Measure J=$28,302,917 Local= $1,679,837
Architect of Record: Roesling Nakamura Terada Architecs, Inc.
General Contractor: BN Builders, Inc.
Project Manager: John Erickson
Program Management: MAAS Companies
Construction Start: October 2023
Anticipated Construction Completion: June 2025
Student Support Center - Project Site
__________________________________________________________________________
Construction Progress Pictures
Upcoming Milestones
- Financial Close-out
Impacts and Closures
- Work is scheduled Monday through Friday from 7:30am to 5:30pm.
- Pedestrian and traffic diversions will occur during portions of construction. Please follow detour signs set up for alternate pathways.
- There will be some noise affecting the public for the duration of construction.
Emergency Contact
- Victor Vasquez (Lead Superintendent): (714) 732-4730
- Rosendo Pantoja (Superintendent): (714) 352-1926
Q2 2026 Project Update
Student Support Center
March - June
Change Order No. 2 was presented to the Board of Trustees along with the Notice of Completion that were approved. The final item required by the DSA Field Engineer is the uninterrupted power supply to provide power in emergency situations to the building automated doors. The items were ordered, installed, and completed by May 1;. Project sign-off is expected to be achieved by the Inspector of Record on projects in the following weeks. The remaining work will be signed off by DSA to achieve final completion.





