Project Overview

Located at the intersections of Chapman Avenue and Newell Street, the Student Support Center will be home to an array of student services vital to their success including the Campus Veterans’ Resource Center, Student Wellness Center (both medical and behavioral health), the Campus Food Bank, Umoja Community Program, Extended Opportunity Programs and Services (EOPS), CalWORKS, Cooperative Agencies Resources for Education (CARE)/Foster Youth Success Initiative (FYSI), a Multi-Cultural Center, and 2 instructional classrooms. In addition, there will be support functions including shared community storage, a department-wide copy, and a breakroom as well as a lactation room for the benefit of all users.

 

Status: Close-Out

Project Costs: Measure J=$28,302,917 Local= $1,679,837

Architect of Record: Roesling Nakamura Terada Architecs, Inc.

General Contractor: BN Builders, Inc.

Project Manager: John Erickson

Program Management: MAAS Companies

Construction Start: October 2023

Anticipated Construction Completion: June 2025

Student Support Center - Project Site

SSC

__________________________________________________________________________

Construction Progress Pictures

Upcoming Milestones

  • Financial Close-out

Impacts and Closures

  • Work is scheduled Monday through Friday from 7:30am to 5:30pm.
  • Pedestrian and traffic diversions will occur during portions of construction. Please follow detour signs set up for alternate pathways.
  • There will be some noise affecting the public for the duration of construction.

Emergency Contact

  • Victor Vasquez (Lead Superintendent): (714) 732-4730
  • Rosendo Pantoja (Superintendent): (714) 352-1926

Q2 2026 Project Update

Student Support Center 

March - June

Change Order No. 2 was presented to the Board of Trustees along with the Notice of Completion that were approved. The final item required by the DSA Field Engineer is the uninterrupted power supply to provide power in emergency situations to the building automated doors. The items were ordered, installed, and completed by May 1;. Project sign-off is expected to be achieved by the Inspector of Record on projects in the following weeks. The remaining work will be signed off by DSA to achieve final completion.