Project Overview
Prior to the start of the Anaheim Tower First Floor Life/Safety Renovation project, involving repairs due to water intrusion at the upper deck parking lot, most first-floor activities were relocated to temporary classrooms and facilities located at the East Parking Lot of the Anaheim-NOCE Campus. Approximately 14 new temporary modular buildings were procured for NOCE's ongoing instruction and administrative activities. Relocation activities will ensue from the Euclid Center, Building B, and Swin Space — Interim Housing in phases between May and August 2025.
Status: Dismantling
Project Estimate: Measure J=$1,650,000 ; RDA and Local=$1,913,335;
Architect of Record: SVA Architects, Inc.
General Contractor: RT Contractor Corp
Project Manager: Matt Pirayeh
Program Management: MAAS Companies
Swing Space / Interim Housing - Project Site

_____________________________________________________________________
Construction Progress Pictures
Upcoming Milestones:
- Financial Close-Out
Impacts and Closure
- Work is scheduled Monday - Friday from 7:30 to 5:30 PM
- Expect some noise during the placement of the modular buildings
- Users of the East Parking Lot will be redirected to the main parking lot and west parking lot during construction.
- Access to shipping and receiving is unaffected.
Emergency Contact:
Matt Pirayeh: (310) 739-1198
Q3 2025 Project Update
Swing Space Projects / Interim Housing
July - August
The Campus Project Team and MAAS Companies, Inc., coordinated the return of personnel temporarily located at the Euclid Center and Printing Shop Department in June. The former building user group (BUG) resumed occupancy at the Anaheim Tower on June 6, while the latter transitioned to its original location in mid-June.
Starting on August 5, the modular buildings began the process of disconnecting and dismantling to allow for Mobile Modular to remove the temporary structures from the project site on August 18. This work is expected to conclude by the first week of September.