Project Overview

Considered the first phase of the New Performing Arts Complex project, the Wilshire Chiller Plant will be relocated adjacent to its original location to accommodate the future construction of the New Performing Arts Complex in its original building footprint. The facilities deliver temperature control to the buildings in its vicinity, including the Wilshire Center. The new facility will provide the same service to the current buildings in addition to the new Performing Arts Complex. The relocation of the infrastructure will be carried in coordination with the local utility, Southern California Edison (SCE).

 

Status: Construction

Project Costs: Measure J=$14,772,894

Architect of Record: Pfeiffer Partners Architects, Inc.

General Contractor: Plumbing, Piping, Construction, Inc.

Project Manager: Aaron Choi

Program Management: MAAS Companies

Construction Start: May 2024

Anticipated Completion: December 2025

 

Wilshire Chiller Plant - Project Site

wilshire site

Construction Progress Pictures

Upcoming Milestones

  • CMU Wall Installation
  • Underground MEP
  • Slab on Grade Pours
  • Wall Framing

Impacts and Closures

  • Working is scheduled Monday - Friday From 7:00 AM to 4:30 PM
  • Expect some noise during construction

Emergency Contact

  • Nick Lopez: (714) 209-2386

Q1 2025 Project Update

Wilshire Chiller Plant Relocation

The demolition of electrical and fiber encasements around the building perimeter continued until the end of the first week of April. As sections of encasements were removed, their trenches were filled in and compacted. In the second week of April, over-excavation and compaction of the chiller building were carried out, followed by survey work for elevations, flooring, and building corners.

Pile drilling commenced in early April. As the holes were excavated, reinforcement bar cages were placed inside, followed by concrete pouring. The concrete foundation piles were poured and are curing. The installation of the foundation grey beams began in the last week of April. Concrete-Masonry-Unit (CMU) walls began installation in mid-May. Electrical and mechanical piping trenching and installation were underway in the third week of the month. The new gas line near Lemon Street will be completed by the end of April, with backfilling finished by the second week of May. The installation of a new building sewer line will commence in the last week of April. Over-excavation for the compressor room is expected to be completed at the start of May.