Project Overview

Considered the first phase of the New Performing Arts Complex project, the Wilshire Chiller Plant will be relocated adjacent to its original location to accommodate the future construction of the New Performing Arts Complex in its original building footprint. The facilities deliver temperature control to the buildings in its vicinity, including the Wilshire Center. The new facility will provide the same service to the current buildings in addition to the new Performing Arts Complex. The relocation of the infrastructure will be carried in coordination with the local utility, Southern California Edison (SCE).

 

Status: Close-Out

Project Costs: Measure J=$16,487,409

Architect of Record: Pfeiffer Partners Architects, Inc.

General Contractor: Plumbing, Piping, Construction, Inc.

Project Manager: Aaron Choi

Program Management: MAAS Companies

Construction Start: May 2024

Completion: March 2026

 

Wilshire Chiller Plant - Project Site

wilshire site

Construction Progress Pictures

Impacts and Closures

  • Working is scheduled Monday - Friday From 7:00 AM to 4:30 PM
  • Expect some noise during construction

Emergency Contact

  • Nick Lopez: (714) 209-2386

 Q3 2026 Project Update

Wilshire Chiller Plant Relocation

July - August 

The project is in the final stages of closeout, with closeout documents collected and archived. On June 23, the Board of Trustees approved a deductive change order that resulted in $66K in project savings, along with the Notice of Completion. The Notice of Completion was filed with the Clerk-County Recorder on July 15. The Financial Team finalized contract costs before releasing retention to the general contractor, PPC, in mid-August.