Project Overview

Considered the first phase of the New Performing Arts Complex project, the Wilshire Chiller Plant will be relocated adjacent to its original location to accommodate the future construction of the New Performing Arts Complex in its original building footprint. The facilities deliver temperature control to the buildings in its vicinity, including the Wilshire Center. The new facility will provide the same service to the current buildings in addition to the new Performing Arts Complex. The relocation of the infrastructure will be carried in coordination with the local utility, Southern California Edison (SCE).

 

Status: Construction

Project Costs: Measure J=$13,645,248

Architect of Record: Pfeiffer Partners Architects, Inc.

General Contractor: Plumbing, Piping, Construction, Inc.

Project Manager: Aaron Choi

Program Management: MAAS Companies

Construction Start: May 2024

Anticipated Completion: August 2025

 

Wilshire Chiller Plant - Project Site

wilshire site

Construction Progress Pictures

Upcoming Milestones

  • Demolition Activities
  • Site Utilities
  • Relocation of Electrical Lighting Control Panel

Impacts and Closures

  • Working is scheduled Monday - Friday From 7:00 AM to 4:30 PM
  • Expect some noise during construction

Emergency Contact

  • Nick Lopez: (714) 209-2386

Q4 2024 Project Update

Wilshire Chiller Plant Relocation

Negotiations for the cost of relocating existing utilities have concluded with PPC and subcontractors JSB, KDC, and VectorUSA, among others. The final cost for the relocation of unforeseen utilities was presented as Change Order No. 1 to the Board of Trustees on November 12 and approved.

Construction activities pertaining to Change Order No. 1 began on November 18, starting with the revised fencing and demolition for unforeseen underground conditions. Crews are anticipated to begin excavation of trenches in the coming weeks.