Scope:
High priority project to increase the square footage and provide new accommodation of services for the Veterans’ Resource Center (VRC)/Student Activities Center (SAC) Expansion.
Status:
The New Veterans' Resource Center (VRC) and Student Activities Center (SAC) finishes are being installed following the completion of the mechanical, electrical, and plumbing components. Acoustical ceiling grid, ceiling light fixtures, and sprinkler and fire alarm components are in progress at the VRC with the SAC to follow.
Construction work proceeds at the site during the current Stay At Home directive from the State's Governor. Sundt is following recommendations from the CDC on social distancing and hygiene practices for all its employees and subcontractors.
Project Estimate:
$13,500,000
Campus Project Manager:
Michael Zari
District Director, Facilities Planning & Construction:
Richard Williams
Program Management:
MAAS Companies